PERMALIGHT® PROJECT SERVICE |HOSPITALS / NURSING HOMES

Delivery and installation of a safety guidance system for kitchen, logistics, nurturing and care areas.

  • Kitchen, logistics, nurturing and care areas
  • 4 floors, 3 staircase
  • Illumination: Fluorescent tube between 50 and 450 Lux, partial day light

  • Coordination with the client
  • Survey
  • Planning of the quanitites
  • Creating an installation drawing
  • Issue of an estimate
  • Delivery safety guidance system:
    • Aluminium grating markers (floor and stairs)
    • Polycarbonate floor markers (stairs)
    • Door latch
    • Push / Pull stickers for doors
    • Signage (floor ID, egress signage and prohibition signage)
  • Installation
  • Documentation (as fitted as)

July 2008

  • First contact between the client and the architect

August 2008

  • First consultation on site
  • Coordination with the chief engineer

September 2008

  • Second visit on site
  • Creating an installation drawing at a charge
  • Quantity counts
  • Estimate on the delivery, installation and documentation

February 2008

  • The client awards the contract to Permalight ®

March / April 2009

  • Delivery
  • Installation by in-house staff after being trained by Permalight

May 2009

  • Creating documentation and invoicing