PERMALIGHT® PROJECT SERVICE|HOSPITALS / NURSING HOMES

Delivery and installation of a safety guidance system in an administration building and staircases.

  • Administration building and staircases
  • 4 floors, 3 staircases
  • Illumination fluorescent tubes with 50 to 450 lux, partial day light

  • Coordination with the project architect
  • Quantity count
  • Creating an installation drawing
  • Estimate
  • Delivery of a safety guidance system
    • Polycarbonate floor markings
    • Polycarbonate signage
    • Polycarbonate guidance strips for the floor
    • Guidance strips for the wall
    • Door frame marking
    • Door latch
    • Casting resin
    • Standard signage with luminance quality ‘power’
    • Special signage
  • Installation
  • Creating an acceptance certificate

June 2007

  • First visit to on site inspection
  • Quantity count including installation drawing
  • Estimate

July 2007

  • Installation of the guidance system after being awarded the contract
  • Presence during walkthrough for acceptance
  • Creating the acceptance report